Aerial photo of the new Gordonvale water treatment plant buildings, clarifiers and reservoir under construction
Case studyWater · Utilities

Cairns Water Security Stage 1

Intake, treatment plant & pipelines · Gordonvale, QLD · In progress

Client
Cairns Regional Council
Project value
$472M
Status
Construction, due 2027
Our role
Area Manager – Pipelines & Intakes
Commissioning Manager

The challenge

Cairns Water Security Stage 1, the largest infrastructure project Council has ever undertaken, includes a new Mulgrave River intake, a treatment plant and reservoirs at Gordonvale, and around 30 km of pipelines through cane farms and across cane rail, the rail corridor, state roads and waterways.

What was delivered

  • Area Manager for the pipelines and intakes within Council's site team, since October 2024
  • Design reviews, including trenchless crossings, raw water mains and the intake
  • Quality surveillance, inspections and non-conformance management
  • Assessment of contractor change requests and claims on Council's behalf
  • Tracking of approval conditions and cultural heritage requirements
  • Commissioning Manager on Council's behalf
  • Regular drone progress records, and aerial photos for Council's social media posts
Aerial photo of a new concrete reservoir under construction on a hillside above Gordonvale
Beyond project managementArea Manager for the pipelines and intakes, Commissioning Manager, and drone progress & media photography for Council.

The outcome

Construction is almost complete and commissioning has commenced. When complete in 2027, the project will supply up to 60 ML of drinking water a day, securing Cairns' water supply for decades to come.

$472MCouncil's largest ever infrastructure project
60 MLa day of new drinking water supply
~30 kmpipelines across farmland, cane rail, rail corridor & state roads